Public Utility Notice to Real Property Owner
Concerning requiring a public utility to provide written notice to an owner of real property before beginning a project that will require the use of the real property.
Official status: Lost
Prime sponsors
- Stephanie Luck (House) — Prime Sponsor
Progress (from the official record)
Official summary
Official text — shown in English exactly as published by the official source. The official text controls.
The bill requires a public utility to provide, at least 90 days before beginning the construction or extension of a new facility, line, plant, or system, notice by certified mail to each owner of private real property that will be used as a result of the construction or extension and to publish notice in a newspaper of general circulation in the area of the real property. The bill requires a public utility to host at least one in-person public meeting at least 30 days after, but no later than 60 days after, providing notice. (Note: This summary applies to this bill as introduced.)
Status timeline
| Date | Location | Action |
|---|---|---|
| 02/19/2026 | House | Introduced In House - Assigned to Energy & Environment |
| 03/12/2026 | House | House Committee on Energy & Environment Postpone Indefinitely |
Recorded votes
- 03/12/2026 — House Energy & Environment: “Refer House Bill 26-1279, as amended, to the Committee of the Whole.” — the motion failed on a vote of 2–10.
- 03/12/2026 — House Energy & Environment: “Postpone House Bill 26-1279 indefinitely using a reversal of the previous roll call. There was no objection to the use of the reverse roll call, therefore, the bill was postponed indefinitely.” — the motion passed on a vote of 10–2.
Proposed amendments (1 proposed amendment)
| Amendment | Committee / floor hearing | Offered | Disposition | Official document |
|---|---|---|---|---|
| L.001 | Committee amendment — Energy & Environment (House) | 03/12/2026 | Passed | View official document |
Source: Colorado General Assembly (leg.colorado.gov) · Data as of
Full text
Full text — side-by-side reader
Showing the latest official version: Introduced version (official PDF), 02/19/2026
Official text — shown in English exactly as published by the official source. The official text controls.
Second Regular Session Seventy-fifth General Assembly STATE OF COLORADO INTRODUCED HOUSE BILL 26-1279 LLS NO. 26-0784.01 Clare Haffner x6137 HOUSE SPONSORSHIP Luck, SENATE SPONSORSHIP (None), House Committees Senate Committees Energy & Environment A BILL FOR AN ACT CONCERNING REQUIRING A PUBLIC UTILITY TO PROVIDE WRITTEN NOTICE TO AN OWNER OF REAL PROPERTY BEFORE BEGINNING A PROJECT THAT WILL REQUIRE THE USE OF THE REAL PROPERTY.
Bill Summary (Note: This summary applies to this bill as introduced and does not reflect any amendments that may be subsequently adopted. If this bill passes third reading in the house of introduction, a bill summary that applies to the reengrossed version of this bill will be available at http://leg.colorado.gov.) The bill requires a public utility to provide, at least 90 days before beginning the construction or extension of a new facility, line, plant, or system, notice by certified mail to each owner of private real property that Shading denotes HOUSE amendment. Double underlining denotes SENATE amendment.
Capital letters or bold & italic numbers indicate new material to be added to existing law. Dashes through the words or numbers indicate deletions from existing law.
will be used as a result of the construction or extension and to publish notice in a newspaper of general circulation in the area of the real property. The bill requires a public utility to host at least one in-person public meeting at least 30 days after, but no later than 60 days after, providing notice.
Be it enacted by the General Assembly of the State of Colorado: SECTION 1. In Colorado Revised Statutes, 40-5-101, add (5) as follows: 40-5-101. New construction - extension - compliance with local zoning rules - landowner notice - definitions. (5) (a) AT LEAST NINETY DAYS BEFORE BEGINNING THE CONSTRUCTION OR EXTENSION OF A NEW FACILITY, LINE, PLANT, OR SYSTEM, WHICH CONSTRUCTION OR EXTENSION WILL REQUIRE THE USE OF PRIVATE REAL PROPERTY, A PUBLIC UTILITY SHALL PROVIDE SUFFICIENT NOTICE TO EACH OWNER OF THE REAL PROPERTY THAT WILL BE USED, REGARDLESS OF WHETHER THE REAL PROPERTY IS SUBJECT TO A UTILITY EASEMENT.
(b) AT LEAST THIRTY DAYS AFTER, BUT NO LATER THAN SIXTY DAYS AFTER, PROVIDING SUFFICIENT NOTICE IN ACCORDANCE WITH SUBSECTION (5)(a) OF THIS SECTION, A PUBLIC UTILITY SHALL HOST AT LEAST ONE IN-PERSON PUBLIC MEETING IN THE COUNTY WHERE THE CONSTRUCTION OR EXTENSION WILL OCCUR.
(c) AS USED IN THIS SUBSECTION (5), "SUFFICIENT NOTICE" MEANS A LETTER SENT BY CERTIFIED MAIL FROM OR ON BEHALF OF A PUBLIC UTILITY TO AN OWNER OF REAL PROPERTY AND PUBLICATION IN A NEWSPAPER OF GENERAL CIRCULATION WITHIN THE AREA OF THE REAL PROPERTY, WHICH LETTER AND PUBLICATION MUST INCLUDE:
(I) THE NAME, ADDRESS, TELEPHONE NUMBER, AND NAMED POINT OF CONTACT FOR THE PUBLIC UTILITY;
(II) THE REAL PROPERTY ADDRESS;
(III) THE RECORDING NUMBER OF ANY UTILITY EASEMENT OR RECORDED MEMORANDUM OF ANY UTILITY EASEMENT;
(IV) A GENERAL DESCRIPTION OF ANY EXISTING PUBLIC UTILITY SERVICE INFRASTRUCTURE ALREADY LOCATED IN A RELEVANT UTILITY EASEMENT AND THE APPROXIMATE LOCATION OF THE UTILITY EASEMENT;
(V) A CITATION TO THIS SECTION;
(VI) AN ESTIMATED TIME FOR THE START OF CONSTRUCTION;
(VII) A NOTICE THAT INTERESTED PERSONS MAY SUBMIT WRITTEN COMMENTS TO THE PUBLIC UTILITY AT ANY TIME BEFORE THE START OF CONSTRUCTION; AND
(VIII) THE DATE, TIME, AND LOCATION FOR THE PUBLIC MEETING HOSTED BY THE PUBLIC UTILITY PURSUANT SUBSECTION (5)(b) OF THIS SECTION.
SECTION 2.
Act subject to petition - effective date - applicability. (1) This act takes effect at 12:01 a.m. on the day following the expiration of the ninety-day period after final adjournment of the general assembly (August 12, 2026, if adjournment sine die is on May 13, 2026); except that, if a referendum petition is filed pursuant to section 1
(3) of article V of the state constitution against this act or an item, section, or part of this act within such period, then the act, item, section, or part will not take effect unless approved by the people at the general election to be held in November 2026 and, in such case, will take effect on the date of the official declaration of the vote thereon by the governor.
(2) This act applies to public utility construction or extension projects commenced on or after the applicable effective date of this act.
Official record
View HB26-1279 on leg.colorado.gov
Source: Colorado General Assembly (leg.colorado.gov) · Data as of
Verify this record
This record carries a fingerprint of its official content, computed by our data pipeline with the SHA-256 algorithm — a real computation over the record itself, not a badge we award ourselves. Anyone can recompute it from the official source and compare.
SHA-256 fingerprint
13d400a06ba2d8b8eb62b917c48fa751f908203e6bb9de7d80544328b161e152
What it covers: the record exactly as the official source publishes it — its identifiers (bill number, session, jurisdiction), its official title and long title, its official summary, its status, its sponsors in published order, every recorded action, every recorded vote, and the link to each official text version — assembled in a fixed canonical form described on the How this data works page.
The fingerprint does not cover our retrieval date (the “Data as of” stamp in the source line): re-fetching unchanged official content produces the same fingerprint, while any change to the official content changes it.
If you recompute the fingerprint from the official source and get a different value, one of us is out of date — please report it through the corrections log.