Official status: Became Law

10 proposed amendments

Prime sponsors

Progress (from the official record)

Official summary

Official text — shown in English exactly as published by the official source. The official text controls.

The act requires the division of administration in the department of public health and environment (division), no later than July 2029, to propose a final rule (rule) establishing certain limits on the emission of nitrogen oxides and sulfur dioxide (emission limits) from an electric generating unit (unit) that is owned or operated by an electric utility; is located in the state; and emitted 200 tons or more of nitrogen oxides, or sulfur dioxide, or both in calendar year 2024 (covered unit). The rule must require compliance with the emission limits as soon as practicable after December 31, 2034, and must not cover units that, before December 31, 2029, have ceased operations; burn natural gas, fuel oil, or both only; or have certain systems installed. A unit that operates after December 31, 2034, must install certain pollution controls and comply with the emission limits on or before December 31, 2034. An owner or operator of a unit is required to provide quarterly emission reports showing compliance with the rule to the division. On August 1, 2029, the air quality control commission in the department of public health and environment (AQCC) must submit to the general assembly a list of any units that are subject to a federal order. If there are any units subject to a federal order, the AQCC must also submit to the general assembly recommendations on whether to amend the requirements for units subject to federal order. An investor-owned utility or wholesale electric cooperative that is the owner or operator of a unit is required, beginning 150 days after the issuance of a federal order requiring the unit to remain operating after the unit was scheduled to retire (order) and continuing every 90 days until the order is no longer in effect, to file a report with the public utilities commission (commission) that contains certain information about the costs to operate the unit and the amount of electricity generated by the unit. The commission must make these reports publicly available. An investor-owned utility is also permitted to submit an application for a financing order to recover the costs of complying with an order. Any decision by the commission approving or modifying a portfolio in an electric resource plan of an investor-owned utility serving more than 500,000 customers must approve an amount of accredited capacity that allows the investor-owned utility to reliably achieve certain retirement and carbon dioxide emission reduction requirements. This requirement applies to an investor-owned utility serving more than 500,000 customers until the division determines that the investor-owned utility has achieved certain carbon dioxide emission reductions or until the investor-owned utility has retired all covered units, whichever is later. (Note: This summary applies to this bill as enacted.)

Status timeline

Every recorded action on HB26-1226, oldest first
DateLocationAction
02/18/2026HouseIntroduced In House - Assigned to Energy & Environment
02/26/2026HouseHouse Committee on Energy & Environment Refer Amended to Appropriations
04/21/2026HouseHouse Committee on Appropriations Refer Amended to House Committee of the Whole
04/21/2026HouseHouse Second Reading Special Order - Passed with Amendments - Committee
04/22/2026HouseHouse Third Reading Passed - No Amendments
04/24/2026SenateIntroduced In Senate - Assigned to Transportation & Energy
04/29/2026SenateSenate Committee on Transportation & Energy Refer Amended to Senate Committee of the Whole
05/01/2026SenateSenate Second Reading Laid Over to 05/04/2026 - No Amendments
05/04/2026SenateSenate Second Reading Passed with Amendments - Committee
05/05/2026SenateSenate Third Reading Passed - No Amendments
05/06/2026HouseHouse Considered Senate Amendments - Result was to Laid Over Daily
05/07/2026HouseHouse Considered Senate Amendments - Result was to Concur - Repass
06/03/2026HouseSigned by the Speaker of the House
06/03/2026SenateSigned by the President of the Senate
06/03/2026GovernorSent to the Governor
06/04/2026GovernorGovernor Signed

Recorded votes

Proposed amendments (10 proposed amendments)

Amendments proposed to HB26-1226, oldest first
AmendmentCommittee / floor hearingOfferedDispositionOfficial document
L.001Committee amendment — Energy & Environment (House)02/26/2026PassedView official document
L.003Committee amendment — Appropriations (House)04/21/2026PassedView official document
L.004Committee amendment — Transportation & Energy (Senate)04/29/2026PassedView official document
L.005
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document
L.006
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document
L.007
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document
L.009
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document
L.008
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document
L.010
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document
L.011
Sponsor: Senator Simpson
Floor amendment — Second Reading (Senate)05/04/2026LostView official document

Source: Colorado General Assembly (leg.colorado.gov) · Data as of

Full text

Full text — side-by-side reader

Showing the latest official version: Signed Act version (official PDF), 06/04/2026

Official text — shown in English exactly as published by the official source. The official text controls.

0 HOUSE BILL 26-1226

BY REPRESENTATIVE(S) Willford and Froelich, Bacon, Brown, Camacho, Clifford, Garcia, Goldstein, Hamrick, Mabrey, McCormick, Nguyen, Sirota, Smith, Stewart R., Story, Titone, Valdez, Velasco, Woodrow, Zokaie, Boesenecker, English, Jackson, Joseph, Lindsay, Paschal, Rutinel, McCluskie, Duran, Mauro; also SENATOR(S) Weissman and Cutter, Kipp, Wallace, Amabile, Benavidez, Danielson, Hinrichsen, Jodeh, Coleman.

CONCERNING MEASURES TO REDUCE EMISSIONS FROM CERTAIN ELECTRIC GENERA TING UNITS IN THE STATE.

Be it enacted by the General Assembly of the State of Colorado:

SECTION 1. Legislative declaration. ( 1) The general assembly finds that: (a) The federal government has taken a series of actions to override the choices that Colorado electric utilities and state agencies have made; (b) For example, the federal government has ordered a power plant to remain available past the closure date that 3 Colorado utilities had decided was in the best interest of their customers;

Capital letters or bold & italic numbers indicate new material added to existing law; dashes through words or numbers indicate deletions from existing law and such material is not part of the act.

(c) Federal actions threaten to raise electricity costs for consumers by requiring utilities to undertake costly repairs for old plants that were scheduled to close, by potentially crowding out cheaper replacement resources, and by forcing customers to pay for the replacement resources and then pay again to keep the plant online that was intended to close; (d) The general assembly has previously authorized the use of a low-cost financing tool, securitization, for certain costs, and it is desirable to allow the use of this tool for costs to comply with a federal order; (e) Federal actions also risk increasing air pollution; (f) In addition, certain power plants in Colorado were constructed several decades ago and have not installed the most modern, effective pollution controls that more recently built power plants have installed;

(g) Electric power plants are the largest stationary sources of air pollution from nitrogen oxides and sulfur dioxide in the state; (h) Certain power plants in the state are currently scheduled to close by the end of 2029; (i) In addition, the general assembly has required that a qualifying retail utility reduce its carbon dioxide emissions 80% by 2030 relative to 2005 levels; U) The qualifying retail utility has also planned to replace certain

older power plants in order to reduce customer costs; and (k) Resource adequacy and reliability are of paramount importance. (2) The general assembly therefore declares that: (a) If certain power plants operate past their currently scheduled retirement dates and into the 2030s, it is appropriate to require that these older plants be modernized to install the most effective pollution controls that are currently available; (b) In order to understand the cost and environmental impacts of

certain federal orders, investor-owned utilities and wholesale electric cooperatives should be required to report on how compliance with certain federal orders will affect Colorado's ratepayers and environment; and ( c)

The public utilities commission should approve enough

resources for a qualifying retail utility to reliably implement its approved plans to replace older power plants and to meet the 2030 clean energy target the general assembly has adopted.

SECTION 2.

In Colorado Revised Statutes, add 25-7-148 as

follows:

25-7-148. Nitrogen oxides and sulfur dioxide emission limits for covered electric generating units after 2034 - rules - quarterly reports - recommendations to the general assembly - definitions.

(1) AS USED IN THIS SECTION, UNLESS THE CONTEXT OTHERWISE REQUIRES: (a) (I) "COVERED ELECTRIC GENERATING UNIT" OR "UNIT" MEANS AN ELECTRIC GENERATING UNIT THAT IS OWNED OR OPERATED BY AN ELECTRIC UTILITY; THAT IS LOCATED IN THE STATE; AND THAT, IN CALENDAR YEAR 2024, EMITTED TWO HUNDRED TONS OR MORE OF NITROGEN OXIDES, TWO HUNDRED TONS OR MORE OF SULFUR DIOXIDE, OR BOTH.

(II) "COVERED ELECTRIC GENERATING UNIT" OR "UNIT" DOES NOT INCLUDE AN ELECTRIC GENERATING UNIT THAT: (A) BURNS NATURAL GAS, FUEL OIL, OR BOTH ONLY; OR (B)

HAS BOTH A FLUE GAS DESULFURIZATION SYSTEM AND A

SELECTIVE CATALYTIC REDUCTION SYSTEM INSTALLED. (b)

"FINAL RULE" MEANS THE FINAL RULE ADOPTED BY THE

COMMISSION PURSUANT TO SUBSECTION (2)(a) OF THIS SECTION. (2) (a) No LATER THAN JULY 2029, THE DIVISION SHALL PROPOSE A FINAL RULE ESTABLISHING LIMITS ON THE EMISSION OF NITROGEN OXIDES AND SULFUR DIOXIDE FROM EACH COVERED ELECTRIC GENERATING UNIT; EXCEPT THAT THE COMMISSION SHALL NOT ESTABLISH EMISSION LIMITS FOR

ACOVEREDELECTRICGENERATINGUNITTHAT,BEFOREDECEMBER3 l,2029, HAS CEASED OPERATIONS, CONVERTS TO BURN NATURAL GAS, FUEL OIL, OR BOTH ONLY, OR HAS BOTH A FLUE GAS DESULFURIZATION SYSTEM AND A SELECTIVE CATALYTIC REDUCTION SYSTEM INSTALLED. (b)

FOR EACH UNIT, THE LIMIT ON THE EMISSION OF NITROGEN

OXIDES IN THE FINAL RULE MUST BE BASED UPON, AND REFLECTIVE OF, OPERATION OF A SELECTIVE CATALYTIC REDUCTION SYSTEM AT THE UNIT. ( c) FOR EACH UNIT, THE LIMIT ON THE EMISSION OF SULFUR DIOXIDE IN THE FINAL RULE MUST BE BASED UPON, AND REFLECTIVE OF, OPERATION OF EITHER A FLUE GAS DESULFURIZATION SYSTEM OR A DRY SPRAY ABSORBER AT THE UNIT.

(d) FOR EACH UNIT, THE COMMISSION SHALL REQUIRE COMPLIANCE WITH THE EMISSION LIMITS REQUIRED BY THE FINAL RULE ON AND AFTER A DATE THAT THE COMMISSION DETERMINES IS PRACTICABLE, WHICH DATE MUST BE AFTER DECEMBER 31, 2034. ( e) A COVERED ELECTRIC GENERA TING UNIT THAT CONVERTS TO BURN NATURAL GAS, FUEL OIL, OR BOTH ONLY IS NOT SUBJECT TO THE EMISSION LIMITS IN THE FINAL RULE.

( t) A COVERED ELECTRIC GENERATING UNIT THAT PLANS TO OPERATE AFTER DECEMBER 31, 2034, AND THAT OPERA TES AFTER DECEMBER 31, 2034, SHALL INSTALL AND OPERATE THE POLLUTION CONTROLS DESCRIBED IN SUBSECTIONS (2)(b) AND (2)( C) OF THIS SECTION ON OR BEFORE DECEMBER 31, 2034, AND MEET THE EMISSION LIMITS ADOPTED PURSUANT TO SUBSECTION (2)(a) OF THIS SECTION UNLESS THE UNIT HAS CEASED OPERATIONS OR HAS CONVERTED TO BURN NATURAL GAS, FUEL OIL, OR BOTH ONLY ON OR BEFORE DECEMBER 31, 2034. (3) THE OWNER OR OPERATOR OF A COVERED ELECTRIC GENERA TING UNIT SHALL PROVIDE QUARTERLY EMISSION REPORTS TO THE DIVISION DEMONSTRATING COMPLIANCE WITH THE FINAL RULE. (4) (a) IN AN ELECTRIC RESOURCE PLAN FILED WITH THE PUBLIC UTILITIES COMMISSION IN WHICH A UTILITY EVALUATES THE OPERATION OF A COVERED ELECTRIC GENERA TING UNIT AFTER DECEMBER 31, 2034, THE UTILITY SHALL INCLUDE AN ESTIMATE OF THE COSTS TO COMPLY WITH THIS

SECTION.

(b) A UTILITY THAT DOES NOT FILE AN ELECTRIC RESOURCE PLAN WITH THE PUBLIC UTILITIES COMMISSION IS ENCOURAGED TO INCLUDE AN ESTIMATE OF THE COSTS TO COMPLY WITH THIS SECTION IN AN EVALUATION OF THE OPERATION OF A COVERED ELECTRIC GENERA TING UNIT AFTER DECEMBER 31, 2034, AND TO MAKE THE ESTIMATE PUBLICLY AVAILABLE. (5) (a) ON AUGUST 1, 2029, THE COMMISSION SHALL SUBMIT TO THE GENERAL ASSEMBLY A LIST OF ANY COVERED ELECTRIC GENERA TING UNITS THAT ARE SUBJECT TO AN ORDER ISSUED BY THE UNITED STATES DEPARTMENT OF ENERGY UNDER SECTION 202 (c) OF THE FEDERAL POWER ACT.

(b) IF THERE ARE ANY COVERED ELECTRIC GENERATING UNITS THAT, AS OF THE DATE OF THE SUBMISSION OF THE LIST DESCRIBED IN SUBSECTION (5)(a) OF THIS SECTION, ARE SUBJECT TO AN ORDER ISSUED BY THE UNITED STATES DEPARTMENT OF ENERGY UNDER SECTION 202 (c) OF THE FEDERAL POWER ACT, THE COMMISSION SHALL ALSO SUBMIT ALONG WITH THE LIST DESCRIBED IN SUBSECTION (5)(a) OF THIS SECTION RECOMMENDATIONS TO THE GENERAL ASSEMBLY FROM STAKEHOLDERS, INCLUDING UTILITIES THAT OWN OR OPERATE COVERED ELECTRIC GENERA TING UNITS, REGARDING WHETHER TO AMEND THIS SECTION, INCLUDING WHETHER TO POSTPONE THE EARLIEST COMPLIANCE DEADLINE DESCRIBED IN SUBSECTION (2)( d) OF THIS SECTION OR ENACT ANY OTHER AMENDMENTS REGARDING COVERED ELECTRIC GENERATING UNITS SUBJECT TO AN ORDER ISSUED UNDER SECTION

202 (c) OF THE FEDERAL POWER ACT. SECTION 3. In Colorado Revised Statutes, add 40-2-141 and 40-2-142 as follows: 40-2-141. Requirements for electric generating units subject to a federal order - reporting - cost recovery - applicability- definitions. (1) As USED IN THIS SECTION, UNLESS THE CONTEXT OTHERWISE REQUIRES: (a) "ORDER" MEANS AN ORDER THAT:

(I)

IS ISSUED BY THE PRESIDENT OF THE UNITED STATES, A

REPRESENTATIVE OF THE FEDERAL GOVERNMENT, OR A FEDERAL AGENCY; AND

(II) REQUIRES A UNIT TO REMAIN AVAILABLE OR CONNECTED TO THE ELECTRIC GRID TO TRANSMIT OR GENERA TE ELECTRICITY AFTER THE DATE THAT THE UNIT WAS SCHEDULED TO RETIRE IN ACCORDANCE WITH AN ELECTRIC RESOURCE PLAN APPROVED BY THE COMMISSION OR THE UTILITY'S GOVERNING ENTITY PRIOR TO THE ISSUANCE OF THE ORDER.

(b) "UNIT" MEANS AN ELECTRIC GENERATING UNIT IN THE STATE. (c) "WHOLESALE ELECTRIC COOPERATIVE" HAS THE MEANING SET FORTH IN SECTION 40-2-134 (2). (2) (a)

(I)

BEGINNING ONE HUNDRED FIFTY DAYS AFTER THE

ISSUANCE OF AN ORDER OR ONE HUNDRED FIFTY DAYS AFTER THE EFFECTIVE DATE OF THIS SECTION, WHICHEVER IS LATER, AND CONTINUING EVERY NINETY

DAYS

UNTIL THE ORDER IS

NO

LONGER

IN

EFFECT,

AN

INVESTOR-OWNED UTILITY OR A WHOLESALE ELECTRIC COOPERATIVE THAT IS THE OWNER OR OPERATOR OF A UNIT SUBJECT TO THE ORDER SHALL FILE A REPORT WITH THE COMMISSION IN THE DOCKET OF THE INVESTOR-OWNED UTILITY'S OR WHOLESALE ELECTRIC COOPERATIVE'S PENDING OR MOST RECENT ELECTRIC RESOURCE PLAN, WHICH REPORT MUST CONTAIN THE FOLLOWING INFORMATION, TO THE EXTENT THE INFORMATION IS AVAILABLE: (A)

THE TOTAL OPERATIONS AND MAINTENANCE EXPENSES

REQUIRED TO KEEP THE UNIT AVAILABLE OR TO OPERATE THE UNIT DURING THE PRECEDING NINETY DAYS; (B) THE TOTAL CA PITAL EXPENDITURES INCURRED TO KEEP THE UNIT AVAILABLE OR OPERATE THE UNIT DURING THE PRECEDING NINETY DAYS;

(C) THE TOTAL NUMBER OF HOURS THAT THE UNIT GENERATED ELECTRICITY DURING THE PRECEDING NINETY DAYS;

(D) THE ELECTRICAL OUTPUT OF THE UNIT DURING THE PRECEDING NINETY DAYS; AND (E) ANY CURTAILMENT OF RESOURCES CAUSED BY THE ORDER AND THE INCREMENTAL COST OF THE CURTAILMENT.

(II) AN INVESTOR-OWNED UTILITY OR A WHOLESALE ELECTRIC COOPERATIVE MAY COMPLY WITH SUBSECTION (2)( a)(I) OF THIS SECTION BY SUBMITfING INFORMATION TO THE COMMISSION THAT THE OPERATOR FILES WITH A FEDERAL AGENCY IF THE INFORMATION ADDRESSES THE TOPICS REQUIRED BY SUBSECTION (2)(a)(I) OF THIS SECTION.

(Ill) IF AN INVESTOR-OWNED UTILITY IS AN OWNER, BUT NOT THE OPERATOR, OF A UNIT SUBJECT TO AN ORDER, THE INVESTOR-OWNED UTILITY SHALL FILE REPORTS WITH THE COMMISSION, ACCORDING TO THE SCHEDULE SPECIFIED BY SUBSECTION (2)(a)(I) OF THIS SECTION, DISCLOSING THE INVESTOR-OWNED UTILITY'S SHARE OF THE TOTAL COSTS SPECIFIED IN SUBSECTIONS (2)(a)(I)(A) AND (2)(a)(l)(B) OF THIS SECTION. (b) (I)

EXCEPT AS SET FORTH IN SUBSECTION (2)(b )(II) OF THIS

SECTION, THE COMMISSION SHALL MAKE INFORMATION PROVIDED PURSUANT TO SUBSECTION (2)(a) OF THIS SECTION PUBLICLY AVAILABLE.

(II) IF AN INVESTOR-OWNED UTILITY OR WHOLESALE ELECTRIC COOPERATIVE

DESIGNATES

INFORMATION

PROVIDED

PURSUANT

TO

SUBSECTION (2)(a) OF THIS SECTION AS CONFIDENTIAL, THE COMMISSION SHALL MAKE THAT INFORMATION AVAILABLE ONLY TO A PERSON THAT HAS SIGNED

AND

FILED

WITH

THE

COMMISSION

THE

APPROPRIATE

NONDISCLOSURE AGREEMENT REQUIRED BY COMMISSION RULES. (3) AN INVESTOR-OWNED UTILITY MAY SUBMIT AN APPLICATION FOR A FINANCING ORDER PURSUANT TO SECTION 40-41-103 TO RECOVER THE COSTS OF COM PL YING WITH AN ORDER, EITHER AS A STAND ALONE APPLICATION OR AS PART OF A BROADER FINANCING ORDER APPLICATION THAT THE INVESTOR-OWNED UTILITY CHOOSES TO SUBMIT PURSUANT TO SECTION 40-41-103.

(4) NOTWITHSTANDING ANY PROVISION OF THIS SECTION TO THE CONTRARY, THIS SECTION APPLIES ONLY: (a) TOTHEOWNEROROPERATOROF A UNIT THAT IS SUBJECTTOAN ORDER AND THAT IS REQUIRED TO FILE AN ELECTRIC RESOURCE PLAN WITH THE COMMISSION; (b) DURING THE TIME PERIOD THAT AN ORDER IS IN EFFECT; AND

(C) TO THE EXTENT NOT INCONSISTENT WITH AN ORDER.

40-2-142. Requirements for commission review of portfolio consisting of supply-side resources - applicability - definition. (1)

As USED IN THIS SECTION, UNLESS THE CONTEXT OTHERWISE

REQUIRES, "COVERED ELECTRIC GENERATING UNIT" HAS THE MEANING SET FORTH IN SECTION 25-7-148 (l)(a).

(2) ANY DECISION BY THE COMMISSION APPROVING OR MODIFYING A PORTFOLIO IN AN ELECTRIC RESOURCE PLAN OR ANY RELATED PROCEEDING IN WHICH THE COMMISSION EVALUATES THE ACQUISITION OF SUPPLY-SIDE RESOURCES FOR AN INVESTOR-OWNED UTILITY SERVING MORE THAN FIVE HUNDRED THOUSAND CUSTOMERS MUST APPROVE AN AMOUNT OF ACCREDITED CAPACITY THAT ENABLES THE INVESTOR-OWNED UTILITY TO RELIABLY: (a)

IMPLEMENT THE RETIREMENT DATES OR OPERATIONAL

RESTRICTIONS IN EFFECT AT THE TIME OF THE COMMISSION'S DECISION REGARDING COVERED ELECTRIC GENERA TING UNITS; AND

(b)

COMPLY WITH ANY APPLICABLE STATE LAW REQUIREMENTS,

INCLUDING THE REQUIREMENTS TO REDUCE CARBON DIOXIDE EMISSIONS DESCRIBED IN SECTION 40-2-125.5.

(3) THE COMMISSION SHALL DETERMINE IN WRITING IN THE WRITTEN DECISION APPROVING OR MODIFYING THE PORTFOLIO THAT THE PORTFOLIO MEETS

THE

ACCREDITED

CAPACITY

REQUIREMENTS

DESCRIBED

IN

SUBSECTION (2) OF THIS SECTION.

(4) NOTHING IN THIS SECTION SHALL BE CONSTRUED TO ALTER THE COMMISSION'S AUTHORITY OR OBLIGATION, IN STATUTE OR IN RULE AS OF THE EFFECTIVE DATE OF THIS SECTION, TO CONSIDER FACTORS IN THE APPROVAL OF A PORTFOLIO, INCLUDING COST AND RATE IMPACTS, IF THE PORTFOLIO THE COMMISSION APPROVES COMPLIES WITH THE ACCREDITED CAPACITY REQUIREMENTS DESCRIBED IN SUBSECTION (2) OF THIS SECTION.

( 5) THIS SECTION APPLIES TO AN INVESTOR-OWNED UTILITY SERVING MORE THAN FIVE HUNDRED THOUSAND CUSTOMERS UNTIL THE DIVISION OF ADMINISTRATION

IN

THE

DEPARTMENT

OF

PUBLIC

HEALTH

AND

ENVIRONMENT DETERMINES THAT THE INVESTOR-OWNED UTILITY HAS ACHIEVED THE CARBON DIOXIDE EMISSION REDUCTIONS DESCRIBED IN SECTION 40-2-125.5 (4)(c) OR UNTIL THE INVESTOR-OWNED UTILITY HAS RETIRED EACH COVERED ELECTRIC GENERA TING UNIT OWNED OR OPERATED BY THE INVESTOR-OWNED UTILITY, WHICHEVER IS LATER.

SECTION 4. Severability. If any provision of this act or the application of this act to any person or circumstance is held invalid, the invalidity does not affect other provisions or applications of the act that can be given effect without the invalid provision or application, and to this end the provisions of this act are declared to be severable. SECTION 5. Applicability. This act applies to conduct occurring on or after the effective date of this act. SECTION 6. Safety clause. The general assembly finds, determines, and declares that this act is necessary for the immediate preservation of the public peace, health, or safety or for appropriations for

the support and maintenance of the departments of the state and state institutions.

Julie McCluskie SPEAKER OF THE HOUSE OF REPRESENTATIVES

James Rashad Coleman, Sr. PRESIDENT OF THE SENATE

Vanessa Reilly CHIEF CLERK OF THE HOUSE OF REPRESENTATIVES

Esther van Mourik SECRETARY OF THE SENATE

APPROVED on Thursday June 4th 2026 at 12:30pm (Date and Time)

Jared S. Polis GOVERNOR OF THE STATE OF COLORADO

Official record

View HB26-1226 on leg.colorado.gov

Source: Colorado General Assembly (leg.colorado.gov) · Data as of

Verify this record

This record carries a fingerprint of its official content, computed by our data pipeline with the SHA-256 algorithm — a real computation over the record itself, not a badge we award ourselves. Anyone can recompute it from the official source and compare.

SHA-256 fingerprint

08efe1eb8afee2f73992059e9a501cc382d787d2c5239c3479f14f6705f9dfd5

What it covers: the record exactly as the official source publishes it — its identifiers (bill number, session, jurisdiction), its official title and long title, its official summary, its status, its sponsors in published order, every recorded action, every recorded vote, and the link to each official text version — assembled in a fixed canonical form described on the How this data works page.

Computed 2026-11-06 · Algorithm: SHA-256 · Canonical form: rogata-canonical-v1

Source: Colorado General Assembly (leg.colorado.gov) · Data as of