HB26-1099 · Bill · 2026 Regular Session · Colorado

Protect Financial Condition of Homeowners Associations

Concerning protecting the financial condition of common interest communities.

Official status: Became Law

2 proposed amendments

Prime sponsors

Progress (from the official record)

Official summary

Official text — shown in English exactly as published by the official source. The official text controls.

The act requires the declarant of a new planned community or condominium, prior to transfer of control from the declarant to the association of a planned community or condominium, to obtain and pay for a reserve study for the planned community or condominium. The study must estimate the projected costs of maintaining, repairing, or replacing the common elements or property of the planned community or condominium over a 30-year period. The reserve study must be conducted by an independent reserve study professional or other qualified professional with knowledge of industry standards and that has no business relationship with or financial interest in the declarant and is not a affiliate of the declarant. When an association, other than a self-managed association, changes association management companies, the former association management company shall, within 45 days, deliver to the new association management company or the association, at no charge to the association, all association property, records, money, accounts, information, and other items or information specified in the act (property and records). Unless otherwise agreed in writing, the former association management company shall pay the association $250 for each business day that it fails to timely return the association's property and records and is liable for all interest and late fees on late payments made by the association due to the former association management company's failure to turn over the property and records, as well as any other damages incurred by the association. In a civil action to recover the property and records or the payments owed to the association for the former association management company's failure to turn over the property and records, if the court finds that the former association management company's violation was willful, the former association management company shall be liable for treble the association's actual damages, plus reasonable attorney fees and court costs. (Note: This summary applies to this bill as enacted.)

Status timeline

Every recorded action on HB26-1099, oldest first
DateLocationAction
02/03/2026HouseIntroduced In House - Assigned to Transportation, Housing & Local Government
02/18/2026HouseHouse Committee on Transportation, Housing & Local Government Refer Amended to House Committee of the Whole
02/23/2026HouseHouse Second Reading Laid Over Daily - No Amendments
02/24/2026HouseHouse Committee of the Whole Amendment - Change from Passed to Lost
02/24/2026HouseHouse Second Reading Special Order - Passed with Amendments - Committee
02/25/2026HouseHouse Third Reading Laid Over Daily - No Amendments
02/26/2026HouseHouse Third Reading Passed - No Amendments
03/03/2026SenateIntroduced In Senate - Assigned to Local Government & Housing
03/19/2026SenateSenate Committee on Local Government & Housing Refer Unamended to Senate Committee of the Whole
03/24/2026SenateSenate Second Reading Passed - No Amendments
03/25/2026SenateSenate Third Reading Passed - No Amendments
04/01/2026HouseSigned by the Speaker of the House
04/01/2026SenateSigned by the President of the Senate
04/02/2026GovernorSent to the Governor
04/13/2026GovernorGovernor Signed

Recorded votes

Proposed amendments (2 proposed amendments)

Amendments proposed to HB26-1099, oldest first
AmendmentCommittee / floor hearingOfferedDispositionOfficial document
L.002Committee amendment — Transportation, Housing & Local Government (House)02/18/2026PassedView official document
L.003
Sponsor: Representative Titone
Floor amendment — Second Reading (House)02/24/2026PassedView official document

Source: Colorado General Assembly (leg.colorado.gov) · Data as of

Full text

Full text — side-by-side reader

Showing the latest official version: Signed Act version (official PDF), 04/13/2026

Official text — shown in English exactly as published by the official source. The official text controls.

HOUSE BILL 26-1099

BY REPRESENTATIVE(S) Titone and Nguyen, Bacon, Joseph, Lindsay; also SENATOR(S) Kolker and Marchman, Exum, Gonzales J ., J odeh, Kipp, Sullivan, Weissman, Coleman.

CONCERNING PROTECTING THE FINANCIAL CONDITION OF COMMON INTEREST COMMUNITIES.

Be it enacted by the General Assembly of the State of Colorado:

SECTION 1. In Colorado Revised Statutes, add 38-33.3-209.2 as follows:

38-33.3-209.2. Declarant duties - reserve study. ( 1) PRIOR TO TRANSFER OF CONTROL FROM THE DECLARANT TO THE ASSOCIATION OF A

PLANNED COMMUNITY OR CONDOMINIUM, THE

DECLARANT SHALL COMMISSION AND PAY FOR A RESERVE STUDY FOR THE PLANNED COMMUNITY OR CONDOMINIUM, WHICH STUDY ADDRESSES THE COMPONENTS OF THE COMMON ELEMENTS AND PROPERTY THAT THE ASSOCIATION IS RESPONSIBLE FOR MAINTAINING, REPAIRING, OR REPLACING, AS DESCRIBED IN THE DECLARATION. THE RESERVE STUDY MUST PROJECT COSTS OVER A THIRTY-YEAR PERIOD.

Capital letters or bold & italic numbers indicate new material added to existing law; dashes through words or numbers indicate deletions from existing law and such material is not part of the act.

(2) THE RESERVE STUDY DESCRIBED IN SUBSECTION (1) OF THIS SECTION MUST INCLUDE AN ESTIMATE OF THE PROJECTED COST OF MAINTAINING, REPAIRING, OR REPLACING THE COMMON ELEMENTS OR PROPERTY OF THE PLANNED COMMUNITY OR CONDOMINIUM. (3) A RESERVE STUDY REQUIRED PURSUANT TO THIS SECTION MUST BE CONDUCTED BY AN INDEPENDENT RESERVE STUDY PROFESSIONAL OR OTHER QUALIFIED PROFESSIONAL THAT: (a) STUDIES;

HAS KNOWLEDGE OF INDUSTRY STANDARDS FOR RESERVE

(b) HAS NO BUSINESS RELATIONSHIP WITH OR FINANCIAL INTEREST IN THE DECLARANT, OTHER THAN BEING RETAINED BY THE DECLARANT TO CONDUCT RESERVE STUDIES; AND (c) Is NOT AN AFFILIATE OF THE DECLARANT.

SECTION 2. In Colorado Revised Statutes, 38-33.3-209.4, amend (2)(h) and (2)(i); and add (2)U) as follows: 38-33.3-209.4. Public disclosures required - identity of association - agent - manager - contact information. (2) Within ninety days after assuming control from the declarant pursuant to section 38-33.3-303 (5), and within ninety days after the end of each fiscal year thereafter, the association shall make the following information available to unit owners upon reasonable notice in accordance with subsection (3) of this section: (h) The minutes of the executive board and member meetings for the fiscal year immediately preceding the current annual disclosure; and (i) The association's responsible governance policies adopted under section 38-33.3-209.5; AND U) THE MOST RECENT RESERVE STUDY REQUIRED PURSUANT TO SECTION 38-33.3-209.2.

SECTION 3. In Colorado Revised Statutes, 38-33.3-303, amend (9)(1) and (9)(m); and add (9)(n) as follows: 38-33.3-303. Executive board members and officers - powers and duties - reserve funds - audit.

(9) Within sixty days after the unit owners other than the declarant elect a majority of the members of the executive board, the declarant shall deliver to the association all property of the unit owners and of the association held by or controlled by the declarant, including without limitation the following items: (I) Any service contract in which the association is a contracting party or in which the association or the unit owners have any obligation to pay a fee to the persons performing the services; and (m) For large planned communities, copies of all recorded deeds and all recorded and unrecorded leases evidencing ownership or leasehold rights of the large planned community unit owners' association in all common elements within the large planned community; AND (n) FOR PLANNED COMMUNITIES AND CONDOMINIUMS, THE RESERVE STUDY COMMISSIONED BY THE DECLARANT PURSUANT TO SECTION 38-33.3-209.2. SECTION 4. In Colorado Revised Statutes, 38-33.3-317, add (9) as follows: 38-33.3-317. Association records - rules - timely transfer of association money and records to new management company or the association - penalty - civil action - damages - attorney fees.

(9) (a) (I) WHEN AN ASSOCIATION, OTHER THAN A SELF-MANAGED ASSOCIATION THAT HAS NOT RETAINED AN ASSOCIATION MANAGEMENT COMPANY, TERMINATES OR FAILS TO RENEW AN AGREEMENT WITH ITS ASSOCIATION MANAGEMENT COMPANY, WITHIN FORTY-FIVE DAYS AFTER THE TERMINATION OR FAILURE TO RENEW THE AGREEMENT, THE FORMER ASSOCIATION MANAGEMENT COMPANY SHALL DELIVER TO THE NEW ASSOCIATION MANAGEMENT COMPANY OR TO THE ASSOCIATION, AT NO CHARGE TO THE ASSOCIATION, ALL ASSOCIATION PROPERTY, INCLUDING

MONEY, FINANCIAL ACCOUNTS, ACCOUNT BOOKS, FINANCIAL RECORDS, INSURANCE POLICIES, CONTRACTS, BUSINESS DOCUMENTS, INVOICES, RECEIPTS, SUBSCRIPTIONS, ACCOUNT INFORMATION, ACCOUNT PASSWORDS, KEYS, AND ANY OTHER PROPERTY OR RECORDS OF THE ASSOCIATION, OR INFORMATION CONCERNING THE ASSOCIATION. (II) SUBSECTION (9)(a)(I) OF THIS SECTION DOES NOT REQUIRE A FORMER ASSOCIATION MANAGEMENT COMPANY TO SUBMIT ANY PROPRIETARY SOFTWARE OR COMPUTER PROGRAMS TO THE ASSOCIATION, SO LONG AS THE ASSOCIATION'S DATA OR RECORDS WITHIN THE PROPRIETARY SOFTWARE OR COMPUTER PROGRAM IS SUBMITTED TO THE ASSOCIATION.

(b)

UNLESS OTHERWISE AGREED IN WRITING BETWEEN THE

ASSOCIATION AND THE FORMER ASSOCIATION MANAGEMENT COMPANY, THE FORMER ASSOCIATION MANAGEMENT COMPANY THAT FAILS TO COMPLY WITH THE REQUIREMENT SET FORTH IN SUBSECTION (9)(a)(I) OF THIS SECTION: (I) IS LIABLE TO THE ASSOCIATION FOR ALL INTEREST AND LA TE FEES ON LATE PAYMENTS MADE BY THE ASSOCIATION DUE TO THE FORMER ASSOCIATION MANAGEMENT COMPANY'S FAILURE TO COMPLY WITH THE REQUIREMENTSETFORTHINSUBSECTION (9)(a)(I) OF THIS SECTION AND ANY OTHER DAMAGES INCURRED BY THE ASSOCIATION DUE TO THE INABILITY OF THE ASSOCIATION TO ACCESS THE ASSOCIATION'S ACCOUNTS, MONEY, PROPERTY, OR INFORMATION SPECIFIED IN SUBSECTION (9)(a)(I) OF THIS SECTION; (II) SHALL PAY TO THE ASSOCIATION TWO HUNDRED FIFTY DOLLARS FOR EACH BUSINESS DAY THAT THE FORMER ASSOCIATION MANAGEMENT COMPANY FAILS TO COMPLY WITH THE REQUIREMENT SET FORTH IN SUBSECTION (9)(a)(I) OF THIS SECTION; AND (III) IN ANY CIVIL ACTION TO ENFORCE THIS SUBSECTION (9), IF THE FORMERASSOCIATIONMANAGEMENTCOMPANY'SVIOLATIONISFOUNDTOBE WILLFUL, SHALL BE LIABLE TO THE ASSOCIATION FOR TREBLE THE ASSOCIATION'S ACTUAL DAMAGES PLUS THE ASSOCIATION'S REASONABLE ATTORNEY FEES AND COURT COSTS.

SECTION 5. Act subject to petition - effective date. This act takes effect at 12:0 I a.m. on the day following the expiration of the

ninety-day period after final adjournment of the general assembly (August 12, 2026, if adjournment sine die is on May 13, 2026); except that, if a referendum petition is filed pursuant to section 1 (3) of article V of the state constitution against this act or an item, section, or part of this act within such period, then the act, item, section, or part will not take effect unless approved by the people at the general election to be held in November 2026 and, in such case, will take effect on the date of the official declaration of the vote thereon by the governor.

Julie McCluskie SPEAKER OF THE HOUSE OF REPRESENTATIVES

James Rashad Coleman, Sr. PRESIDENT OF THE SENATE

Vanessa Reilly CHIEF CLERK OF THE HOUSE OF REPRESENTATIVES

Esther van Mourik SECRETARY OF THE SENATE

APPROVED on Monday April 13th 2026 at 11am (Date and Time)

Jared S. Polis GOVERNOR OF THE STATE OF COLORADO

Official record

View HB26-1099 on leg.colorado.gov

Source: Colorado General Assembly (leg.colorado.gov) · Data as of

Verify this record

This record carries a fingerprint of its official content, computed by our data pipeline with the SHA-256 algorithm — a real computation over the record itself, not a badge we award ourselves. Anyone can recompute it from the official source and compare.

SHA-256 fingerprint

a0437565f59f9790db80b20e07a995c1e246fc0f500f73c741948f503daff5fa

What it covers: the record exactly as the official source publishes it — its identifiers (bill number, session, jurisdiction), its official title and long title, its official summary, its status, its sponsors in published order, every recorded action, every recorded vote, and the link to each official text version — assembled in a fixed canonical form described on the How this data works page.

Computed 2026-11-06 · Algorithm: SHA-256 · Canonical form: rogata-canonical-v1

Source: Colorado General Assembly (leg.colorado.gov) · Data as of